The Avenues Hilton March Progress

What a gorgeous morning on site, and as you can see for yourselves with the photos taken, everything at The Avenues Hilton is taking shape beautifully.

The Avenues Shopping Centre:

  • The shopping centre earthworks platform is complete.
  • Landscaped berm is flourishing (and stood up to the hurricane winds and driving rain – all in tact).
  • We are still fine tuning the speciality tenants who will be located between the 3 main anchor tenants.
  • The Avenues Shopping Centre opening date is now looking to be around  Mid April 2021.

Main Access Road into the Estate:

  • Spine Road Intersection with Hilton College Road is largely complete (some minor snagging, road markings etc are still to be completed).
  • Spine Road tarring is completed to the The Avenues Hilton Gatehouse (this was also delayed with the massive storm events again in February 2020).
  • Landscaping and Irrigation installation along Spine Road is by and large completed (in terms of the avenues of trees)
  • Some additional minor works are still required on the medians and near to the Gatehouse.

The Avenues Residential Estate:

  • The main structural and internal elements of the Gatehouse are largely completed now, with the remainder of the cladding delayed due to supply issues, but still on track.

Enjoy the blue skies and find yourselves a good spot for a coffee and some down time today to enjoy it.

#TheAvenuesHilton #KZNMidlands